Montenegro has issued a construction permit for the first phase of the Sinjajevina wind project near Kolašin, advancing plans for 136 megawatts of renewable electricity capacity in the country’s north.
The Ministry of Spatial Planning, Urbanism and State Property granted the permit to Podgorica-based developer Energy 2. The decision, dated November 4, covers 17 wind turbines rated at eight megawatts each, together with their foundations, in the Lipovska Bistrica area.
Under the permit’s conditions, the developer must begin work within two years of issuance and complete construction within five years. A construction start date has yet to be announced.
Project Advances Through Planning and Environmental Approvals
The permit follows several years of preparation. Montenegro’s government issued the project’s initial urban planning and technical conditions in December 2023, allowing the developer to prepare the engineering documentation.
Podgorica-based Permonte prepared the main design, while Sistem-MNE carried out the technical review. The permitting process also included approval of the environmental impact assessment by Montenegro’s Environmental Protection Agency, alongside clearances from other relevant institutions.
The latest decision moves the project into a stage where financing, construction arrangements and electricity network infrastructure will determine how quickly it progresses.
The planned 136 MW represents the turbines’ combined rated capacity. Actual electricity generation will depend on wind conditions, equipment availability and operating constraints once the facility enters service.
Grid Connection Remains a Key Step
Montenegro’s transmission system operator, CGES, has approved the signing of an agreement for infrastructure to connect the Sinjajevina 1 and Sinjajevina 2 projects to the transmission network.
That infrastructure will provide the route for electricity from the turbines to reach the national power system. Its development will therefore need to align with construction of the generating facilities.
The project also involves contractual deadlines alongside the conditions attached to the construction permit. In October, the ministry proposed an additional 12 months, until October 4, 2027, for the first phase’s contractual timetable. The permit itself sets the separate two-year period for starting work and five-year period for completion.
Earlier planning documents described different turbine specifications. The latest permitting reports identify 17 turbines of eight megawatts each, giving the first phase its stated capacity of 136 MW.
Once built and connected, the development would add another source of wind generation to Montenegro’s electricity system. The next milestones are the start of construction and delivery of the infrastructure needed to transmit its output.